Council estate - increase solar power generation
Implementation Stage
Early Concept/Scoping
Define/Plan
Deliver
Complete
Action Description
Increase PV (photovoltaic) generation across DCC estate by 3MW. This will include a mixture of roof mounted, ground mounted, and vertical mounted, to best suit the site.Target
3MW of solar PV to be installedProgress Update
Procurement for SPA4 (Solar PV Array 4), to deliver 0.5MW of PV across DCC estate began on 11/12/2024. Outside of SPA4, solar PV has been installed at Peterlee Pathways and Corten House. Currently investigating the potential of solar PV at Chilton Depot.Expected Completion Date
31/03/2027
Responsible Organisation
Durham County Council
Carbon Footprint Type
Council
Council Carbon Footprint
Med (>50-200 tonnes)
Countywide Carbon Footprint