Council estate - Jade Business Park solar project

Status

Slightly Off Track

Implementation Stage

Early Concept/Scoping
Define/Plan
Deliver
Complete

Action Description

Develop 1MW solar array at Jade Business Park (following Eastern Green Link construction and construction of National Grid convertor station when field is back with DCC)

Target

1MW installed capacity

Progress Update

Project on hold until post Eastern Green Link (2028)
Expected Completion Date
31/03/2029
Responsible Organisation
Durham County Council
Section Team
Carbon Footprint Type
Council
Council Carbon Footprint
Low (1-50 tonnes)
Countywide Carbon Footprint
Actual Annual Co2 Saving
Cost
£1,000,000
Funding Secured
No