Council estate - Public Sector Decarbonisation Scheme

Status

Slightly Off Track

Implementation Stage

Early Concept/Scoping
Define/Plan
Deliver
Complete

Action Description

Take forward the following first stage decarbonisation plans: Spennymoor EDC Bishop Auckland TH Durham Pathways Chester - le - Street LC Louisa Centre

Target

6 plans complete

Progress Update

Spennymoor EDC - Looking into options for a hybrid heating system. Bishop Auckland TH - Looking at heating options, no current works on site. Durham Pathways - Has had an ASHP (air Source heat pump installed). Chester - le - Street LC - Looking at heating options, no current works on site. Louisa Centre - Looking into decarbonisation works on site.
Expected Completion Date
01/01/2026
Responsible Organisation
Durham County Council
Section Team
Carbon Footprint Type
Council
Council Carbon Footprint
0 Enabling or Adaptation Action
Countywide Carbon Footprint
Actual Annual Co2 Saving
Cost
£24,000
Funding Secured
Yes