HomeClimate change action planTheme: Energy and BuildingsAction: Leisure Centre decarbonisation

Leisure Centre decarbonisation

Status

On Track

Implementation Stage

Early Concept/Scoping
Define/Plan
Deliver
Complete

Action Description

Continue with decarbonising Leisure Centres with target to achieve over 50% fossil fuel free including; Louisa Centre Stanley Freemans Quay - Durham Newton Aycliffe - Ph2 (heat recovery)

Target

7 leisure centres reporting no gas for heating by 2027

Progress Update

Abbey LC, Peterlee LC currently have no gas connection. Newton Aycliffe LC only has gas for peak periods. Next phase will be Louisa centre and Freeman’s Quay and new LC at Bishop Auckland
Expected Completion Date
31/03/2027
Responsible Organisation
Durham County Council
Section Team
Carbon Footprint Type
Council
Council Carbon Footprint
Med (>50-200 tonnes)
Countywide Carbon Footprint
Actual Annual Co2 Saving
Cost
£5,000,000
Funding Secured
No