HomeClimate change action planTheme: Energy and BuildingsAction: Council estate - Top 30 Building Energy Management Systems

Council estate - Top 30 Building Energy Management Systems

Status

On Track

Implementation Stage

Early Concept/Scoping
Define/Plan
Deliver
Complete

Action Description

Increase proportion of top 30 sites covered by Building Energy Management Systems (BEMS)

Target

75% increase

Progress Update

All sites on top 30 list have some form of BEMS on site (ref separate excel sheet) there is a split between functional - functional but require software update - functional but locked out maintenance is carried out yearly on all Service Level Agreement sites with BEMS and issues reported back via compliance and Property Help Desk but not all works under taken due to budget issues. Work is being done to regain control of sites where we are locked out of the BEMS.
Expected Completion Date
31/03/2027
Responsible Organisation
Durham County Council
Section Team
Carbon Footprint Type
Council
Council Carbon Footprint
Low (1-50 tonnes)
Countywide Carbon Footprint
Actual Annual Co2 Saving
Cost
£500,000
Funding Secured