HomeClimate change action planTheme: Energy and BuildingsAction: Council estate - Energy Efficiency Improvement programme

Council estate - Energy Efficiency Improvement programme

Status

Slightly Off Track

Implementation Stage

Early Concept/Scoping
Define/Plan
Deliver
Complete

Action Description

Install energy efficiency and building fabric improvements at 10 sites per year.

Target

10 sites to receive energy efficiency improvements per year

Progress Update

Currently developing plans to deliver energy efficiency improvements throughout the council, but need to identify a budget. Delta T has been rolled out at 3 sites. 3 sites have been identified for energy efficiency improvements.
Expected Completion Date
31/03/2027
Responsible Organisation
Durham County Council
Section Team
Carbon Footprint Type
Council
Council Carbon Footprint
Low (1-50 tonnes)
Countywide Carbon Footprint
Actual Annual Co2 Saving
Cost
£100,000
Funding Secured
No