HomeClimate change action planTheme: Energy and BuildingsAction: Council estate - Top 10 surveys

Council estate - Top 10 surveys

Status

On Track

Implementation Stage

Early Concept/Scoping
Define/Plan
Deliver
Complete

Action Description

Carry out surveys and heating decarbonisation plans at the remaining significant carbon emitting facilities. Freemans Quay LC Spennymoor LC Green Lane Offices Hackworth Road Depot Chilton Depot

Target

5 surveys complete

Progress Update

Freeman Quay and Green Lane Offices both have PSDS submissions in, along with Crook civic centre under PSDS grant 4.
Expected Completion Date
01/04/2025
Responsible Organisation
Durham County Council
Section Team
Carbon Footprint Type
Council
Council Carbon Footprint
0 Enabling or Adaptation Action
Countywide Carbon Footprint
Actual Annual Co2 Saving
Cost
£30,000
Funding Secured
No