Home Upgrade Grant

Status

Slightly Off Track

Implementation Stage

Early Concept/Scoping
Define/Plan
Deliver
Complete

Action Description

Home Upgrade Grant funding to retrofit measures to private Off gas properties across the County.

Target

250 measures installed

Progress Update

Project ongoing, expected works to around 25-30 properties by end March 2025. Funding was reduced by DESNZ to £620,000 capital for the retrofit works to properties across County Durham. Works due to commence at the end of January 2025.
Expected Completion Date
31/03/2025
Responsible Organisation
Durham County Council
Section Team
Carbon Footprint Type
Countywide
Council Carbon Footprint
Countywide Carbon Footprint
Med (>300 - 600 tonnes)
Actual Annual Co2 Saving
Cost
£5,100,000 (reduced to £620,00 capital by DESNZ)
Funding Secured
Yes